Schedule and Monitoring Document
Production Schedule and monitoring
document
Week
|
Date
|
Activity
|
1
|
13th Jan
|
1 Schedule Creation: this
week I will make sure that I create a realistic schedule to enable me to
submit a completed project for the 15th February in accordance
with the objectives outlined in my treatment. The schedule will be realistic,
detailed and will contain 3 meaningful activities to complete as homework.
Homework activities should take up four
hours additional study time per week.
2 Schedule Creation:
Today I will look at other commitments I have in my other A Levels including
scheduled exams – this will enable me to produce a realistic schedule. In
order to do this I will need to ask my other subject teachers about deadlines
for homework/coursework during the next six weeks.
3 Schedule Creation: Today
I will create my schedule, taking into consideration my future exams, how
long each page in my product will take to create and complete. I will also
respect that some pages will require a little more time and focus than others,
and that problems might arise, however I will deal with these problems in
homework sessions and will assess my progress in weekly Project Monitoring
blog updates.
4 Project Monitoring: I
will introduce what I will be writing about in my Project Monitoring blog
updates, and the difficulties I might face along the way of creating my
project.
4 Schedule Creation: Today
I will continue to create my schedule, taking into consideration my future
exams, how long each page in my product will take to create and complete. I
will also respect that some pages will require a little more time and focus
than others, and that problems might arise, however I will deal with these
problems in homework sessions and will assess my progress in weekly Project
Monitoring blog updates.
Homework 1: Complete Schedule if needed
Homework 2: Complete Schedule if needed
Homework 3: Complete Schedule if needed
|
2
|
20th Jan
|
1
2
3
4 Project Monitoring &
Homework 1:
Homework 2:
Homework 3:
Exams/other
subject deadlines:
|
3
|
27stJan
|
1
2
3
4 Project Monitoring &
Homework 1:
Homework2:
Homework 3:
Exams/other
subject deadlines:
|
4
|
3rd Feb
|
1
2
3
4 Project Monitoring &
Homework 1:
Homework 2:
Homework 3:
Exams/other subject
deadlines:
|
5
|
10th Feb
|
1
2
3
4 Project Monitoring &
Homework 1:
Homework 2:
Homework 3:
Exams/other
subject deadlines:
|
Half term
|
17th Feb
|
Homework:
Complete Monitoring and make sure that blog elements are complete
|
6
|
24th
|
1
2
3
4 Project Monitoring &
Homework 1:
Homework 2:
Homework 3:
Exams/other
subject deadlines:
|
3rd Mar
|
Audience/Assessor
Review Week
1 Create Audience
review questionnaire
2 Teacher
assessment of project
3 & 4
Complete prep work for evaluation E exam
Unit 5 Blog
Deadline 7th
March
|
Tuesday, 7 January 2014
Contingency Plan
Contingency plan
|
Problem
|
How
will you avoid or solve this problem?
|
|
Model
Doesn’t turn up to photo shoot
|
I
will make sure my model knows exactly where and when the shoot will be, I
will also make them turn up thirty minutes early to ensure we start on time.
However I will also have a backup model on hand to step in.
|
|
Props
are forgotten or lost
|
I
will make sure I have all the props in my possession the day before the shoot
and will make sure they are with me at all times.
|
|
Part
of the wardrobe is lost or forgotten
|
I
will bring spare clothes and make sure my model knows exactly what they are
supposed to wear in advance of the shoot; I will also have a team of people
working on wardrobe who will have outfits planned in advance.
|
|
Model
is late to photo shoot
|
Run
through lights and take test shots to make sure lighting is correct. I will
also set up the set whilst I wait for my model to show up. However to avoid
this I will tell my model to turn up thirty minutes early.
|
|
Any
problems with hair and makeup
|
I
will start again and take my time, making sure it’s perfect.
|
|
The
photos do not turn out how I want them too
|
I
will make sure I take my time doing the photo shoot, looking at each photo to
make sure they give me the right image I am going for. If not I will take
lots of different photos for me to choose from later. However if all else
fails, I will book another photo shoot as soon as possible.
|
|
I
lose my files
|
I
will back up all of my files in various places to ensure if one set is lost,
I still have them in a safe place. For example, on multiple, computers, on
the internet, on external devices such as a USB stick.
|
|
InDesign
crashes
|
I
will make sure after every change I do, I will save my progress so that if
InDesign does crash, the changes I have lost, will only be small and I won’t
have to start again.
|
|
I
miss a lesson
|
I
will do extra classes and work through free periods to ensure I have caught
up with work I would have done in lesson.
|
|
My
flat plan doesn’t translate well to my physical product
|
I
will then make a new flat plan and change factors in order to start my
product again, with better chances of looking better. I could also create two
different versions of the product and ask my target audience which one they
prefer.
|
|
Can’t
pick a font
|
I
will make different versions of my product using different fonts, and then
ask my target audience to pick which one they like best.
|
|
I
become behind on my schedule
|
I
will work through extra sessions until I am back on schedule
|